How to install Rail Mounted or EOT Gantry Cranes
Ohayo gozaimasu
Electrical Overhead Travelling (EOT) cranes or Gantry Cranes are commonly found in factory applications such as steel yards, paper mills or locomotive repair shops. The EOT gantry crane functions similarly to an overhead bridge crane, but has rails installed on the ground and gantry-style legs to support the crane. Capacities range from 2 to 200 tons, and sometimes even greater capacities. Most are electrically powered and painted safety yellow.
Overhead cranes, sometimes also called bridge cranes, are cranes with a hoist traveling along the bridge between parallel runways. They are designed to meet the medium to heavy industrial lifting requirements, covering all parts of manufacturing process.
With this post i just want to share knowledge for installing the overhead gantry during construction.
3.0 Assemble
end carriages to 1st girder ( power supply side) and tigten bolts
and nuts
Ohayo gozaimasu
Electrical Overhead Travelling (EOT) cranes or Gantry Cranes are commonly found in factory applications such as steel yards, paper mills or locomotive repair shops. The EOT gantry crane functions similarly to an overhead bridge crane, but has rails installed on the ground and gantry-style legs to support the crane. Capacities range from 2 to 200 tons, and sometimes even greater capacities. Most are electrically powered and painted safety yellow.
Overhead cranes, sometimes also called bridge cranes, are cranes with a hoist traveling along the bridge between parallel runways. They are designed to meet the medium to heavy industrial lifting requirements, covering all parts of manufacturing process.
With this post i just want to share knowledge for installing the overhead gantry during construction.
1.0 PLANT AND MACHINERIES
1.0 60 ton mobile crane -
1 Nos
2.0 trailer - 1 Nos
3.0 20 tonne x 19m length Overhead Crane - 4 Nos
Model : CXT6062P6FO
Min.
Loaded Hoisting Speed = 4/0.7m/min @ 60% ED
Hoist Group
: Fem 3m.
2 Nos girder
: 9.00 Tonne ( 4.5Tonne/girder)
1 nos of
hoist : 2.30Tonne
2 Nos end
Carriages:1.17Tonne
2.0 DOULBLE
GIRDER E.O.T CRANE INSTALLATION PROCEDURE (BY MOBILE CRANE)
A. Crane Erection
Inside Building
1.0 proposed indicating area
required site clearance for mobile crane and trailer parking for the
unloading, assembly and erection of overhead crane (Area
of 30m(length) x 20m ( width-crane span) at each bay).
2.0 Erection work will be carried out inside
building.
B. Crane Installation
1.0 A complete double girder crane is made
up the following major part:
i)
Girders
ii)
End carriages
iii)
Hoist
iv)
Flat cable power supply and mobile control system
v)
Other smaller items like long travel control box,
end stopper, limit switch and etc.
2.0 Upon
unloading girders from trailers, the girders will be placed on stools at two
ends for
subsequent crane assembly work.
Note: Girders and
end carriages are match-made in factory with matching marks punched on each
item. Re-match the matching marks during installation at site.
(refer
Appendix A).
Note:
When strapping short sling, using soft material around the girder to protect it
from
being
scratched.
5.0 Site
touch up painting.
6.0 Tie 2
manila ropes at each of the end carriages.
7.0 Rotate
the girder so that it makes an angle of approx.45º with the runway and are
position in
between columns.
8.0 Lift
up the girder at the center until it clear the runway. Using the nylon ropes
rotate the
crane
from 45º to 90º ( with the runway ) ( refer to Appendix B ) and slowly lower
crane
onto
runway rails
9.0 Remove
all ropes
11.0
Lift up the hoist with mobile crane and place on top
of girder
12.0
Fix up all electrical wiring and downshop power
supply
13.0
Test each movement of the crane.
Note:
Depends on the availability of power supply.
3.0 SAFETY AND HEALTH
1.0
Regulations
All site activities shall comply strictly
with UEMC Project Health and Safety Plan regulations and requirements. All
staff will also be familiar with the Construction Crisis Team’s Handbook.
2.0 Launching Safety Briefing
A safety briefing will be conducted by the
launcher prior to the launching to ensure that all people involved are familiar
with the works (The Designed Launcher will be fully in charge during the
launching activity). The safety officer will then brief the workers on the
general hazards of slab launching.
3.0
Equipment Checks
The safety officer will check and ensure
that all cranes are fully operational and that there is no irregularities prior
to the launching. The launching will be halted if any irregularities are
observed.
4.0 General
Safety
All workers are to wear PPE equipments such
as safety helmet and safety shoes within
working area. All safety issues will be governed by the Health and Safety Plan
and adhered to strictly.
5.0 Environment Issues
The Environmental Management Plan will be
adhered to strictly on site.


Ulasan ini telah dialihkan keluar oleh pengarang.
BalasPadam